Project overview

BlueScope – Metal Coating Line 7

  • Erskine Park, NSW
  • Bluescope
  • Prime Constructions
  • 4 Series

Airocle used CFD to design ventilation for areas with different heat loads at BlueScope’s Western Sydney Service Centre. The supply and installation scope included make-up air louvres positioned to provide the inlet airflow required by the design.

CFD-led natural ventilation for BlueScope’s Metal Coating Line 7

Airocle designed, supplied and installed a natural ventilation system for BlueScope’s Metal Coating Line 7 (MCL7) at the Western Sydney Service Centre in Erskine Park, NSW. The work included acoustic 4 Series roof ventilators and make-up air louvres, and the design addressed both process heat and smoke hazard management.

MCL7 is part of BlueScope’s $415 million investment at Erskine Park. The new line is designed to add 240,000 tonnes of ZINCALUME® steel coating capacity per year and support production of products such as TRUECORE® and COLORBOND® steel.

The challenge: different heat loads across the facility

BlueScope provided heat-load data for the high, medium and low bays, as well as the ingot storage area. Each area had a different ventilation demand. Airocle used the data to assess how warm air would rise through the building and where replacement air needed to enter.

The solution: model the air path from wall to roof

Airocle used computational fluid dynamics (CFD) modelling to develop the ventilation layout. The design positioned make-up air louvres to provide the inlet airflow needed to support heat removal through the acoustic 4 Series roof ventilators. The resulting layout gave incoming air a defined path through the building and warm air an outlet at roof level.